Configuration of multiperiod variable batch units for complex products in cloud manufacturing mode
Download as PDF
DOI: 10.25236/icemit.2019.031
Author(s)
Du Yi, Chen Qingxin, Mao Ning
Corresponding Author
Du Yi
Abstract
In order to find an effective approach to decrease tardiness of the heat transfer element with no increase of equipment and human resource cost on one hand, and to enhance productivity on the other hand, the paper proposes to establish an integer programming model. The paper uses the branch and bound method to address the first issue, whose results are analyzed to acquire the optimal solution under the principle of POSP-FM scheduling. With examples, the paper verifies the effectiveness of decreasing tardiness with no increase of equipment cost and human resources cost, and provides advices on the way to construct multichannel so as to decrease tardiness.
Keywords
The variable production line, Tardiness quantity, Branch and bound, Equipment cost, Human resource cost, Heat transfer element